Otuke, Uganda — Local leaders in Otuke District have stepped up their oversight of ongoing government infrastructure projects, calling for transparency, quality assurance, and timely delivery as works progress on the Bua Simon–Police road upgrade.

The 0.868km road, located in the heart of Otuke Town, is currently being sealed under the Rural Transformation Infrastructure (RTI) program.
The project, valued at UGX 313,472,310, is funded by the Government of Uganda and supervised by the District Engineering Department.
The contractor, Bosceno Enterprises Ltd, began work on February 19, 2025, with the official completion date set for June 15, 2025.
As of April 8, key components of the project have been successfully executed, including:
1. Full mobilization of equipment and materials.
2. Installation of culverts and drainage systems per design standards.
3. Completion and testing of the road’s sub-base and base layers.
4. Stabilization of the road base, with test results from the Ministry of Works’ Mbale Laboratory confirming compliance.
However, the contractor is yet to begin bituminous surfacing and auxiliary works due to delays in procuring bitumen and chippings from Kenya—an issue that could affect the final timeline.
A high-level inspection team comprising RDC George Abudul, Assistant RDC Isaac Opio Opeo, LCV Chairperson Francis Abola, DISO Denis Otim, CAO Joseph Lomongin, and other district officials visited the site to assess progress.
Otuke Chief Administrative Officer Joseph Lomongin commended the district’s procurement team for selecting capable contractors and affirmed that, “as the accounting officer, we remain committed to the timely implementation of all projects—ranging from school renovations and road rehabilitation to staff houses and toilets—which have been launched, commissioned, or are nearing commencement.”
RDC George Abudul praised the central government for investing in rural infrastructure but reminded the contractor of their duty to deliver value for every shilling spent.
“This project is funded by taxpayers. We shall not tolerate shoddy work. President Museveni has done his part by providing the peace and funding—now it’s up to you, the implementers, to match that with quality and efficiency,” Abudul asserted.
In response, Bosceno Enterprises Ltd pledged to complete the works on time and within budget. The company acknowledged the procurement delays but assured the leadership that remedial plans were underway to recover lost time and avoid compromising quality.
The district engineering team, led by Eng. Jimmy Alany Max reaffirmed their commitment to rigorous supervision and regular updates to both the public and relevant government agencies.
The project has ignited hope among local residents, many of whom depend on the road for access to schools, health centers, markets, and administrative services.